Wired for conflict? The circuit breaker you installed and never switched on

​Africa is wiring up for an energy revolution, but an overlooked fault is tripping the circuit. Dispute risk is quietly draining returns, derailing commissioning timelines and sending a chilling signal to the market. Every year, billions of dollars of African energy infrastructure investment lose power in the same place: the arbitration hearing room.

If your project is under construction and a dispute arises, data from multiple global institutions show that arbitration will likely take years and millions of dollars per side to resolve. That is not a legal problem. It is a wiring problem.

Your contract almost certainly contains a Dispute Avoidance and Adjudication Board (DAAB) clause – the missing conductor. It is almost certainly not switched on.

Here is how to wire it in before the fault becomes a blackout.

A grid under strain: the power drain nobody is accounting for

Africa faces a well-documented energy crisis. Hundreds of millions of people lack reliable access to electricity and closing that gap requires a sustained influx of private and institutional investment into generation, transmission and distribution infrastructure. When investment stalls, when a project sits idle, when delays mount or when a developer walks away, the consequences are felt not on​ly on a balance sheet but in homes, hospitals and businesses that remain without power.

What is not widely understood is that disputes between project participants, developers, contractors, utilities and governments, are among the primary and least discussed reasons that energy investment stalls in Africa.

To understand why, consider how disputes compound the other risks that investors already know about. Political risk, regulatory uncertainty and financing gaps all slow projects down. Disputes do something more damaging: they can lock projects in place entirely. An active arbitration freezes decision-making, ties up management, drains capital and signals to the broader market that a project, or even a country, is too difficult to operate in.

ICC data confirms that energy disputes consistently rank among Africa's top arbitration sectors1, with complex infrastructure arbitrations routinely consuming years of management time and substantial costs on all sides. Three years of arbitration on a project designed to commission in two years means stranded capital, continued power deficits and a clear signal to the market that the risk outweighs the return.

The consequences extend far beyond the parties to the dispute. When South Africa’s Medupi and Kusile power station programmes became entangled in protracted contractor disputes, arising from the complexity of constructing two of the world’s largest coal-fired power stations and compounded by concurrent design changes, skills shortages and industrial action, the result was not merely financial loss.2 It contributed directly to South Africa's loadshedding crisis, as the generating capacity those stations were designed to deliver remained offline, delayed by disputes that effective avoidance mechanisms could have prevented or substantially curtailed.

This is the power drain nobody is accounting for: the energy that is never generated, the investment that is never deployed and the capacity that is never commissioned because a dispute that could have been resolved in weeks was allowed to become an arbitration that lasted years.

The tools to prevent this exist. They are contractual. They are relatively cheap. And they are being systematically ignored.

The clause you signed and forgot

Here is the uncomfortable truth for almost every client active in African energy infrastructure: your DAAB clause is probably inactive.

The DAAB, introduced in the Fédération Internationale des Ingénieurs-Conseils (FIDIC) 2017 suite of contracts, is one of the most powerful dispute-prevention mechanisms available to the sector. It is a small panel of independent construction law and engineering experts appointed at the outset of a project that engages continuously throughout construction, visiting the site, receiving regular reports and issuing informal recommendations before problems crystallise into claims. Where a formal dispute does arise, it delivers a binding decision within 84 days.

In our experience, the DAAB clause is routinely included and almost as routinely ignored. Named panel members are not appointed. Site visit schedules are not agreed. Engagement protocols are never activated. The clause sits dormant in the contract while the project accumulates the unresolved tensions that will eventually force someone to issue a dispute notice.

This is not a niche concern. Engineering, procurement and construction (EPC) disputes are statistically inevitable at the scale now being contemplated across the continent. South Africa's Transmission Development Plan envisages 14,500 kilometres of new transmission infrastructure over the next decade. Offtaker and power purchase agreement (PPA) disputes are widespread. In our experience, escalation rarely stems from a single catastrophic event but rather from the accumulation of smaller unresolved issues, including disputed curtailment calculations, grid availability disagreements and delayed variation processing. These issues harden into entrenched positions because no mechanism exists to resolve them in real time.

Regulatory and tariff disputes pose perhaps the greatest long-term risk. Kenya's experience – where regulatory instability relating to tariff frameworks and PPA terms generated the risk of protracted disputes between developers and Kenya Power – illustrates what happens when the rules governing project economics are reset after financial close in the absence of structured dispute avoidance frameworks.3

Cross-border interconnectors compound all of the above: multiple regulatory regimes, multiple currencies, multiple legal systems and no harmonised dispute resolution framework to govern them.
The question is not whether your project will generate disputes. It is whether you have built the architecture necessary to prevent those disputes from becoming full-blown, costly and protracted arbitrations.

The business case: dispute avoidance is capital preservation

The most common objection to DAABs is cost. It does not survive scrutiny.


Key consideration

DAAB (three-person panel)

International arbitration

Typical cost

Typically 0.05% - 0.25% of project value (≈ USD 50,000 - USD 250,000 on a USD 100 million project)4

Multi‑million per party in complex disputes (roughly ~USD 4 million - USD 7 million+ per party but highly variable) 5

Time to resolution

84 days from referral

Commonly three years or more6

Project disruption

Minimal

Severe

Relationship impact

Generally preserved

Frequently terminal

Management bandwidth

Limited

Very high

A DAAB that operates across a three-year construction programme without ever issuing a formal decision cost less than two weeks of arbitration legal fees.
Consider what avoiding a single significant arbitration is worth in terms of capital preserved, time recovered and relationships maintained. The business case for investing in effective dispute avoidance mechanisms speaks for itself.

The question for an investment committee should therefore be reframed. Dispute avoidance expenditure is not a legal cost. It is an internal rate of return (IRR) protection mechanism. It preserves lender relationships. It keeps management focused on construction rather than disclosure obligations and expert witness preparation. It avoids the reputational signal that active arbitration sends to the market and it keeps the project generating returns rather than consuming them.

For lenders and development finance institutions (DFIs), the calculus is even starker. Arbitration on a project within a portfolio can result in delayed drawdowns, impaired security positions and the prospect of enforcement proceedings across multiple jurisdictions. The independent engineer is already on site, informed and trusted by all parties. Extending that mandate to include structured dispute facilitation costs relatively little. Failing to do so may cost substantially more.

This is not a cost centre. It is capital preservation and it should be approved and activated before ground is broken, not after the first dispute notice is issued.

Your switchboard: the full toolkit

Beyond the DAAB, three mechanisms deserve particular attention.

DAABs done properly

The distinction is between a DAAB clause and an operational DAAB. The former is a contractual formality. The latter has named panel members, an agreed site visit schedule and engagement protocols that are active from day one of construction. Only the latter delivers value.

Early warning and senior escalation mechanisms

The NEC4 (New Engineering Contract, Fourth Edition) suite obliges parties to identify emerging risks before they become claims and requires escalation to executive level before formal proceedings commence. In our experience, a significant proportion of disputes escalated to that level are resolved without proceeding further. The mechanism works because it places the appropriate decision-makers in the room before positions become entrenched.

Enhanced independent engineer mandates

The independent engineer is already on the project, already informed and already trusted by lenders. Extending that role to include structured dispute facilitation function costs relatively little and may prevent substantial losses.

Flipping the switch: three policy changes that cannot wait

The systemic shift required is straightforward.

First, standardised DAAB provisions should be adopted for African transmission contracts - not boilerplate clauses that are signed and forgotten, but operationally active mechanisms with named DAAB members, agreed site visit schedules and clear engagement protocols from day one.

Second, DFI and compact conditionality should require DAAB operationalisation as a condition precedent to first drawdown, as fundamental as the financial model or the environmental and social impact assessment. If institutions such as the World Bank and the African Development Bank required it, the market would likely follow.

Third, a regional dispute avoidance facility should be established - a pre-qualified standing pool of technical and legal experts available to African energy projects on a retainer basis. Such a model could draw on the statutory adjudication frameworks in Hong Kong and the United Kingdom, which maintain standing panels of adjudicators available to construction projects on an institutional basis. The cost would be a fraction of that associated with a single avoided arbitration.

Plugging in: what this means for you

Audience

Activate the DAAB

Audit contracts and templates

Strategic and systemic action

Developers and independent power producers

Require named panel members and an initial site visit as conditions of contract execution, not merely clause inclusion.

Audit power purchase agreements for early warning obligations, senior escalation requirements and technical liaison mechanisms with utility grid operation teams.

Identify and ring-fence enforceable assets at financial close. Enforcement planning after an award is too late

Government ministries and utilities

Treat operational DAAB provisions in public sector procurement as an investor confidence signal, sophisticated avoidance frameworks attract sophisticated capital

Incorporate early warning obligations into standard power purchase agreement templates to surface payment difficulties and curtailment constraints before they become disputes.

Obtain legal advice on stabilisation and change-in-law provisions before implementing regulatory changes that affect existing investors.

Lenders and development finance institutions

Make DAAB operationalisation a verified condition precedent to first drawdown, not a contractual formality.

Expand independent engineer mandates to include dispute monitoring and early warning notice reporting obligations to lender groups.

Advocate institutionally for a regional dispute avoidance facility, it would cost less than one project arbitration and prevent many more.

Corporate counsel

Establish internal escalation protocols that mirror contractual requirements so that dispute notices trigger clear governance pathway immediately.

Audit standard contract templates against the FIDIC DAAB framework and NEC4 early warning standards, close the gaps in the next negotiation cycle.

Brief your boards on the financial imbalance between dispute avoidance and dispute resolution using concrete commercial metrics. In precise financial terms: dispute avoidance investment is far easier to approve when decision-makers understand what they are avoiding.

Wire it in

Africa's energy deficit cannot afford the years and billions of dollars that arbitration can consume. The lessons from Medupi, from the continent's independent power producer payment disputes and from comparable markets across Asia and Latin America are consistent: dispute risk is a structural feature of large-scale infrastructure development and its consequences in Africa extend beyond financial returns to the continued absence of reliable power for people who cannot afford to wait.

The tools exist. The numbers are compelling. Your circuit breaker is probably already wired into your contract. The only question is whether you are going to switch it on before the surge arrives or after the damage has been done.

The circuit is not complete without dispute avoidance. Wire it in.


1 - International Chamber of Commerce, ICC Dispute Resolution Statistics: 2024, ICC International Court of Arbitration (2025), available at: https://iccwbo.org/news-publications/news/icc-dispute-resolution-statistics-2024/.

2 - South African Parliament Standing Committee on Public Accounts (SCOPA), Report on its Oversight Visit to Eskom and its Infrastructure Projects of Medupi and Kusile, 20 to 22 April 2022 (ATC220530), available at: https://pmg.org.za/tabled-committee-report/4960/

3 - Republic of Kenya, Press Release: Report of the Presidential Taskforce on the Review of Power Purchase Agreements, Office of the President (September 2021), available at: Press-Release-Report-of-the-Presidential-Taskforce-on-PPAs-13.-00-Hrs-Engrossed.pdf.

4 - Engineering News-Record, DARBs in Construction: How Dispute Avoidance and Resolution Boards Save Time, Money, and Relationships, Engineering News-Record (24 June 2025), available at: https://www.enr.com/articles/60944-darbs-in-construction-how-dispute-avoidance-and-resolution-boards-save-time-money-and-relationships

5 - Hodgson M, Kryvoi Y and Hrčka D, Costs, Damages and Duration in Investor-State Arbitration, British Institute of International and Comparative Law (June 2021), available at: https://www.biicl.org/documents/136_isds-costs-damages-duration_june_2021.pdf

6 - Hodgson et al, Costs, Damages and Duration (n 3 above).


Disclaimer

These materials are provided for general information purposes only and do not constitute legal or other professional advice. While every effort is made to update the information regularly and to offer the most current, correct and accurate information, we accept no liability or responsibility whatsoever if any information is, for whatever reason, incorrect, inaccurate or dated. We accept no responsibility for any loss or damage, whether direct, indirect or consequential, which may arise from access to or reliance on the information contained herein.


© Copyright Webber Wentzel. All Rights reserved.

Webber Wentzel > News > Wired for conflict? The circuit breaker you installed and never switched on
Johannesburg +27 (0) 11 530 5000
|
Cape Town +27 (0) 21 431 7000
Validating email against database, please wait...
Validating email: please wait...
Email verified: Please click the confirmation link sent to your mailbox, also check junk/spam folder. If you no longer have access to this email address or haven't received the verification email then email communications@webberwentzel.info
Email verified: You are being redirected to manage your subscription
Email could not be verified: Please wait while you are redirected to the Subscription Form
Unanticipated error: Saving your CRM information Subscription Form